The Framing Inspection: What Gets Checked

What an inspector looks at during a framing inspection in Alberta, when it happens in the sequence, and the items that most often cause a re-inspection.

By David Hutten, Owner, Green Ladder Contractors

The Framing Inspection: What Gets Checked - Green Ladder Contractors, Red Deer and Central Alberta

The framing inspection happens after the structure is complete and the mechanical rough-ins are in, and before anything covers them up. Once insulation and drywall go on, none of it can be seen again, so the timing matters.

Where It Sits in the Sequence

  1. Framing complete
  2. Plumbing, electrical, and HVAC rough-ins in
  3. Those trades pass their own inspections
  4. Framing inspection
  5. Insulation and vapour barrier
  6. Drywall

Booking it too early, before the rough-ins are done, generally means a second visit. Booking it after insulation means opening the wall back up.

What the Inspector Is Actually Looking At

Structural members and their sizes. Joists, studs, beams, and headers matching what the approved drawings specify. Substitutions that were not on the drawings are a common finding.

Headers over openings. Sized for the span they cross. Inspectors check these closely because an undersized header has real consequences.

Bearing and load paths. Where loads come down, and whether what they land on can carry them. A beam landing on something that was not designed for a point load is one of the things this inspection is there to catch.

Connectors and fasteners. Hangers, straps and ties present where specified, and installed with the fasteners the connector is rated for. Missing or wrong hanger nails come up often in corrections.

Sheathing and its nailing pattern. The nail schedule is what makes the sheathing do its structural job. Overdriven nails, missed edges, and wrong spacing all show up here.

Notching and boring. Whether services run through the structure stay within what is allowed. A joist cut in the wrong place carries less, and it cannot be seen after drywall, so inspectors look for this specifically.

Fire blocking and separations, where applicable, including between an attached garage and living space.

Egress. Any bedroom needs a window meeting the egress requirement. In basement developments this is the most common reason work has to be redone, because fixing it means cutting concrete (a framing correction would be far simpler).

Anything with an engineer stamp being built as the stamped drawings show.

The Most Common Corrections

From experience across Central Alberta, the recurring items:

Missing or wrong fasteners in rated connectors. Easy to fix, frequently found.

Notched or bored members beyond what is allowed. Usually this happens when a line gets run after the framing is done and nobody had planned the route.

Missing fire blocking.

Header sizes that do not match the drawings.

Bracing on trusses not to the truss drawings.

Most of these take an afternoon to correct, and the wait for the re-inspection is usually the longer part.

How Framing Avoids Most of This

2 habits prevent the majority of findings.

Plan the mechanical routes at layout. With boxing and bulkheads planned before the trades arrive, nobody has to drill structure to make room, and that removes the most common category of correction.

Build to the drawings, including the hardware schedule. The hardware schedule is part of the design, and we install each rated connector with the fasteners it is rated for.

Who Calls It In

On our projects we apply for the permit on your behalf (you sign a letter authorizing us to), and the inspection sits under that permit. In practice we coordinate the timing, have the work ready, and are on site to answer questions.

An inspection called before the work is complete goes on the record as failed, and then there is a wait for the next slot.

What Happens After a Correction Notice

The items get corrected and a re-inspection is booked. This is routine. What matters is that the corrections are made and not just covered over, because the next inspection in the sequence, and eventually the occupancy or final approval, depends on it.

The bad outcome is work getting closed up before it passed. That tends to come up later at a sale or a claim, when the wall is already finished.

The Practical Takeaway

The framing inspection is a helpful checkpoint. It is the one time everything structural is visible at once, and the last look before it all goes behind drywall for the life of the building.

Green Ladder frames to the drawings and to the stamp, has the work ready in the right inspection sequence, and plans the mechanical routes at layout so nobody has to cut into structure later to make room.

Our Work

Framing & Structural Carpentry

Garage, basement, and subcontract framing across Red Deer and Central Alberta.

See Our Framing & Structural Carpentry Work →

Before you sign a quote: What a complete framing quote includes

DH

David Hutten

Owner, Green Ladder Contractors

David Hutten started building at age 10 and has more than 30 years of hands-on construction experience. Green Ladder Contractors renovates kitchens, bathrooms and basements and builds home additions, garages and decks across Red Deer and Central Alberta.

Ready to start your project?

Book a free 15-minute discovery call. We'll walk through your vision, budget, and timeline.

Project Tips & Updates

Project inspiration, building tips, and seasonal updates. One email per month.